Eastside Industrial Coatings Addition
Project Details
Project Name: Eastside Industrial Coatings Addition
Client: Triple D Developments
Project Manager: Hans E. Boge, P.Eng.
Boge Resources: Tyler Hiebert (Design Manager & Project Coordinator)
Diaser Resources: John Mueller (Construction Manager)
Square Footage: 30,000 ft2
Project Initiation: 2021
Project Completion: 2023
Project Description
Diaser Management (2006) Ltd. provided design and construction of a new 30,000 sqft building addition and adjacent 1,000 sqft link at the Eastside Industrial Composites manufacturing facility located at 2262 Springfield Road in Sunnyside, Manitoba.
The project provided a connection between two existing buildings and undertook modifications to the exiting building’s heat, power and sprinkler systems. Construction needed to be coordinated with exiting manufacturing needs, timelines and climatic conditions including a site electrical shutdown to facilitate power upgrades.