MCC Thrift Store - Storage Expansion

Project Details

Project Name: Design Build - Storage Expansion

Client: MCC Thrift Store

Project Manager: Hans E. Boge, P. Eng.

Boge Resources: Tyler Hiebert (Designer & Project Coordinator)

Diaser Resources: John Mueller (Construction Manager)

Square Footage: 3,193 ft2

Project Initiation: January 2020

Project Completion: 2021


Project Description

Construction of the new expansion included the following items:

  • Concrete slab on grade | Complete with piling, excavation, backfill, concrete, rebar, and rigid insulation.

  • Masonry walls | Complete exterior masonry walls with required rigid insulation, and interior metal liner finish.

  • Roof assembly | Complete roof assembly with joists, metal deck, and modified bitumen roof.

  • Mechanical | Complete drainage, heating, cooling, and ventilation.

  • Electrical | Complete lighting, power, and fire alarm extension.

  • Doors | Complete supply and installation of overhead sectional doors and exterior doors.

  • Renovations | Lunchroom wall to be moved east to expand corridor to the new expansion. All millwork will be removed and reinstalled. Removal of interior doors and expansion of doorways. Temporary Receiving opening.

  • Repair of exterior asphalt around new expansion

Design and Engineering of the new expansion included the following items:

  • Review of existing building and review of integration of expansion with current operation.

  • Completion of Issued for Construction Engineering Drawings for Architectural, Structural, Mechanical, and Electrical disciplines.

  • Regular site visits and provided documentation indicating satisfactory work and conformance to the engineering drawings.

  • Review and revisions to engineering drawings as site conditions became visible.